McKenzie Electric Cooperative, Inc (MEC) Grassy Butte Transmission Line Upgrade Project.
The Forest Service has received a proposal for the upgrade of approximately three miles of an existing 41.6kV transmission line across National Forest System Lands.
Project Summary
Location Summary:
North of Hwy 200 and East of Hwy 85
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 06/07/2013 |
Comment Period | 06/07/2013 |
Decision | 11/2013 (Estimated) |
Implementation | 12/2013 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (2), 36 Cfr 220.6(E)(2)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Mckenzie Ranger District
Notice and Comment Regulation:
215
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Completed
Project Decision Information
McKenzie Electric Coop Grassy Butte Poweline Upgrade
Decision Signed Date: 11/14/2013
Legal Notice Date: 11/19/2013
Forests:
Dakota Prairie Grasslands
Districts:
Mckenzie Ranger District
States:
North Dakota
Counties:
McKenzie
Legal Land Description:
Sections 18, 19, 20 and 20, T145N, R98W and Section 13, T145N, R99W, 5th PM, McKenzie County, North Dakota.
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Jeff Ingalls
1905 Main St. South
Watford City, ND 58854-6705
701-842-2393
jingalls@fs.fed.us
Last Updated: 12/17/2013