Bridger Pipeline LLC's Little Missouri Loop Pipeline
Construct approximately 10 miles of 16-inch steel crude pipeline in various sections, T138-140N, R100-103W, Billings and Golden Valley counties, North Dakota.
Project Summary
Location Summary:
Starts north of Fryburg and leaves Forest Service land 12 miles east of Golva, North Dakota
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 06/15/2016 |
| Comment Period | 06/15/2016 |
| Objection Period Start | 03/2019 (Estimated) |
| Decision | 05/2019 (Estimated) |
| Implementation | 05/2019 (Estimated) |
Expected Analysis Type:
Environmental Assessment
Special Authority:
Not Applicable / Other
Lead Management Unit:
Medora Ranger District
Notice and Comment Regulation:
218 (2013) Non-HFRA
Project Purpose:
Minerals And Geology; Special Use Management
Project Activity:
Special Use Authorizations; Oil
Current Status:
Cancelled
Forests:
Dakota Prairie Grasslands
Districts:
Medora Ranger District
States:
North Dakota
Counties:
Billings; Golden Valley
Legal Land Description:
S 23-24, 27, 29-30, T138N, R102W, Golden Valley Co.; S 1, 11, 15, 18, T138N, R101W; S 13-14-15 & 18, T138N, R102W; S 5, T138N, R100W; S 33, T139N, R100W, S 33, T140N, R100W; Billings Co.
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Cathy Walsh
99 23rd Avenue W, Suite B
Dickinson, ND 58601-3135
701-227-7818
cewalsh@fs.fed.us
Last Updated: 2/13/2019