North Range Resources, LLC Rough Rider Eagle 5-1V and 5-2V Surface Use Plan of Operations
North Range Resources, LLC proposes to construct one well pad, utilities and access on the Little Missouri National Grassland to develop private mineral resources.
Project Summary
Location Summary:
Pad location: NENE, Section 5, T.145N., R.100W., 5th PM; Access terminus: NENW of Section 33, T.146N., R100W, 5th PM
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 03/22/2018 |
| Comment Period | 03/24/2018 |
| Objection Period Start | 08/2018 (Estimated) |
| Decision | 10/2018 (Estimated) |
| Implementation | 10/2018 (Estimated) |
Expected Analysis Type:
Environmental Assessment
Special Authority:
Not Applicable / Other
Lead Management Unit:
Dakota Prairie Grasslands All Units
Notice and Comment Regulation:
218 (2013) Non-HFRA
Project Purpose:
Minerals And Geology
Project Activity:
Minerals Or Geology Plans Of Operations; Natural Gas; Oil
Current Status:
Cancelled
Forests:
Dakota Prairie Grasslands
Districts:
Mckenzie Ranger District
States:
North Dakota
Counties:
McKenzie
Legal Land Description:
Pad location: NENE, Section 5, T.145N., R.100W., 5th PM; Access terminus: NENW of Section 33, T.146N., R100W, 5th PM
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Cale Bickerdyke
2000 Miriam Circle
Bismarck, ND 58501
701-227-7800
cebickerdyke@fs.fed.us
Last Updated: 1/27/2020