Bridge replacements in Greenhorn, Adams, Chocolate, & Oregon Gulches
Replacing bridges, and ford rehabilitation on trails in Greenhorn, Adams Gulch, Chocolate Gulch, and Oregon Gulch. Change the first 1.9 miles of Adams Gulch from road to trail designation. No change in alignment.
Project Summary
Current Status:
Completed
Location Summary:
Greenhorn gulch, OregonGulch, Chocolate gulch, adn Adams gulch,
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 03/25/2010 |
| Decision | 07/2010 (Estimated) |
| Implementation | 06/2011 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.12 (4), 36 Cfr 220.6(D)(4)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Ketchum Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Recreation Management
Project Activity:
Trail Management
Project Decision Information
Trail Bridge Construction/Reconstruction and Route Designation Change
Decision Signed Date: 07/15/2010
Trail Bridge Construction/Reconstruction and Route Designation Change
Decision Signed Date: 07/15/2010
Forests:
Sawtooth National Forest
Districts:
Ketchum Ranger District
States:
Idaho
Counties:
Blaine
Legal Land Description:
(T4N, R17E,S15&16), (T4N, R17E, S2&3) (T5N, R17E, S.15) (T5N, R17E, S.10)
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Dan Kenney
P.O. Box 2356
Ketchum, ID 83340
208-622-0094
dkenney@fs.fed.us
Last Updated: 12/21/2010