Mineral Gulch Plan Of Operations Amendment
Amendment to Plan of Operations for additional exploration drilling and preparation of supplement to Environmental Assessment
Project Summary
Current Status:
Completed
Location Summary:
Sawtooth National Forest, Minidoka Ranger District,Black Pine Division, within the area of the former Black Pine Mine
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 11/21/2011 |
| Comment Period | 11/21/2011 |
| Decision | 04/2012 (Estimated) |
| Implementation | 06/2012 (Estimated) |
Expected Analysis Type:
Environmental Assessment
Special Authority:
Not Applicable / Other
Lead Management Unit:
Minidoka Ranger District
Notice and Comment Regulation:
215
Project Purpose:
Forest Products
Project Activity:
Minerals Or Geology Plans Of Operations
Project Decision Information
Decision Notice Mineral Gulch Exploration Project
Decision Signed Date: 04/04/2012
Legal Notice Date: 04/07/2012
Forests:
Sawtooth National Forest
Districts:
Minidoka Ranger District
States:
Idaho
Counties:
Cassia
Legal Land Description:
T15S, R29E, Sections 25, 26, 27, 28, 33, 34, 35, 36;
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Heidie Torrealday
2306 Hiland Ave
Burley, ID 83318
208-678-0430
htorrealday@fs.fed.us
Last Updated: 6/25/2012