Camp Pinedell Additions
Placement of an amphitheater behind the existing stage facility.
Project Summary
Current Status:
Completed
Location Summary:
Camp Pinedell, Cassia Division, Minidoka Ranger District, Sawtooth National Forest
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 06/29/2012 |
| Comment Period | 06/29/2012 |
| Decision | 08/2012 (Estimated) |
| Implementation | 08/2012 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (3), 36 Cfr 220.6(E)(3)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Minidoka Ranger District
Notice and Comment Regulation:
215
Project Purpose:
Special Use Management
Project Activity:
Facility Improvements/Construction
Project Decision Information
Decision Memo Camp Pinedell Amphitheater Stage Construction
Decision Signed Date: 08/13/2012
Forests:
Sawtooth National Forest
Districts:
Minidoka Ranger District
States:
Idaho
Counties:
Cassia
Legal Land Description:
T14S R19E Sec 31
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
David Ashby
2306 Hiland Ave
Burley, ID 83318
208-678-0430
dashby@fs.fed.us