Idaho Military Division Improvements
The proposal is to add an underground propane tank to provide fuel for generated electricity during power outages and to add on to the existing communications building. This will allow for more room to house new and additional equipment.
Project Summary
Current Status:
Completed
Location Summary:
Albion Division of Minidoka Ranger District
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 05/20/2015 |
| Decision | 08/2015 (Estimated) |
| Implementation | 09/2015 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (3), 36 Cfr 220.6(E)(3)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Minidoka Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Project Decision Information
Idaho Military Division Improvements
Decision Signed Date: 08/28/2015
Forests:
Sawtooth National Forest
Districts:
Minidoka Ranger District
States:
Idaho
Counties:
Cassia
Legal Land Description:
Boise Meridian, Township 13 South, Range 24 East, Section 4
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
David Ashby
2306 Hiland Ave
Burley, ID 83318
208-677-8304
dashby@fs.fed.us
Last Updated: 8/31/2015