South Fork Boise River Road Relocation
Camas County and the Sawtooth National Forest propose to relocate segments of the South Fork Boise River Road (Forest Road 227) out of the floodplain around existing washouts in at least four locations in order to reconnect the road between Big Smoky and Featherville.
Project Summary
Current Status:
Completed
Location Summary:
Forest Road 227 (Ketchum-Featherville Road) between Big Smoky and the confluence with the South Fork Boise River.
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 01/10/2018 |
| Comment Period | 01/31/2020 |
| Objection Period Start | 03/09/2020 |
| Decision | 04/2020 (Estimated) |
| Implementation | 06/2020 (Estimated) |
Expected Analysis Type:
Environmental Assessment
Special Authority:
Not Applicable / Other
Lead Management Unit:
Fairfield Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Road Management; Wildlife, Fish, Rare Plants
Project Activity:
Species Habitat Improvements; Road Improvements/Construction
Project Decision Information
Forest Road 227 Realignment (Bowns Washout) Project
Decision Signed Date: 04/28/2020
Forests:
Sawtooth National Forest
Districts:
Fairfield Ranger District
States:
Idaho
Counties:
Camas
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
David Skinner
P.O. Box 189
Fairfield, ID 83327
208-764-3475
dskinner@fs.fed.us
Last Updated: 4/29/2020