Basalt Road Realignment Project
.75 mile of Basalt Road (FR 095) is immediately adjacent to Basalt Creek and subject to damage from seasonal flooding. This project will relocate the road outside of the riparian area, install culverts for drainage and decommission the prior route.
Project Summary
Current Status:
Completed
Location Summary:
Section of Basalt Creek Road (FS 095) in the general vicinity of the Basalt warming hut.
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 11/08/2024 |
| Decision | 06/2025 (Estimated) |
| Implementation | 07/2025 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (24), 36 Cfr 220.6(E)(24)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Fairfield Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Road Management
Project Activity:
Road Decommissioning; Road Maintenance; Road Improvements/Construction
Project Decision Information
Basalt Road Realignment Project
Decision Signed Date: 06/11/2025
Forests:
Sawtooth National Forest
Districts:
Fairfield Ranger District
States:
Idaho
Counties:
Camas
Legal Land Description:
T2N,R4E,S13
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
David Skinner
P.O. Box 189
Fairfield, ID 83327
208-764-3475
david.skinner@usda.gov
Last Updated: 6/12/2025